Vaughan to receive over $23 million in grid enhancements from Alectra to improve reliability
Electric line workers on a bucket truck

Vaughan, ON – Alectra Utilities is addressing increasing customer electricity demands by reinforcing its power grid in the City of Vaughan. In 2023, Alectra is investing $23 million in the city to meet the growing need for reliable electricity. 

“Delivering safe and reliable electricity to our customers is our top priority” said Mike Matthews, Executive Vice President of Asset Strategy and Operations at Alectra. “We are committed to investing in new technologies that will not only help prevent power outages but also minimize environmental impacts while offering a lower-cost alternative for our customers.” 

With parts of Vaughan’s system nearing the end of its life cycle, Alectra is taking steps now to renew deteriorating infrastructure. These upgrades are necessary to maintain reliability and stabilize the existing system to reduce outage impacts in the community. 

Alectra is introducing new technologies to increase efficiencies and reduce costs. One of those technologies is an innovative process called cable injection, which repairs, protects, and extends the life of underground cables without digging them up. For every kilometre of cable injection, Alectra avoids approximately 13 tonnes of greenhouse gas (GHG) emissions. To date, Alectra has injected more than 820 km of underground cable across its service territories, avoiding over 10,000 tonnes of GHG emissions. 

In 2023, Alectra plans to continue to invest in capital renewal projects across Vaughan, including: 

  • $9.7M to rehabilitate underground cable through cable injection. 
  • $10.1M to renew aging infrastructure including poles, transformers, switchgear renewal and new automation. 
  • $2.0M in station upgrades, enhancing efficiency and performance. 
  • $585,346 to construct new lines to accommodate growth. 
  • $1.2M to construct net new automated devices for faster restoration and to construct new communications equipment. 

Alectra Utilities is committed to investing in the electricity grid across all 17 communities it serves to support growth and to continue to provide safe and reliable service. Learn more about our commitment to reliability at alectrautilities.com/improving-reliability

About Alectra Utilities 

Serving more than one million homes and businesses in Ontario’s Greater Golden Horseshoe area, Alectra Utilities is now the largest municipally-owned electric utility in Canada, based on the total number of customers served. We contribute to the economic growth and vibrancy of the 17 communities we serve by investing in essential energy infrastructure, delivering a safe and reliable supply of electricity, and providing innovative energy solutions. Our mission is to be an energy ally, helping our customers and the communities we serve to discover the possibilities of tomorrow’s energy future. 


Media Contact 

Ashley Trgachef, Media Spokesperson ashley.trgachef@alectrautilities.com | Telephone: 416.402.5469 | 24/7 Media Line: 1-833-MEDIA-LN

Download News Release PDF

Is your location?